    ASME PCC-1 provides the industry-standard instructions for assembling bolted bride joints in pressure systems.This document is part of the Post Construction Code (PCC) series from the American Society of Mechanical Engineers.It addresses one of the most common failure points in any facility:the flange interface.

    It moves beyond simple “tightening” and introduces a scientific approach to joint integrity.By adhering to these guidelines,companies prevent leaks,reduce emissions and ensure the longevity of their tuyaux et raccords de tuyauterie.

    What is the Purpose of ASME PCC-1?

    ASME PCC-1’s primary objective is to achieve leak-free joints during initial startup and long-term operation.Bolted joints are complex mechanical systems involving the interaction of flanges,bolts and gaskets.Failure of any single component or uneven assembly puts the entire system at risk.
    Covering the entire process from visual inspection to final torque sequence,this standard minimizes the risk of human error during critical installation phases.Whether installing large-diameter flanges or small valves,these principles apply.

    Ce que nous faisons

    • Plaque
    • Feuille
    • Forgeage
    • Barre ronde
    • Bride
    • Tuyaux
    • Raccords
    • Sur mesure

    Contactez-nous pour plus d'informations 

    Achieving Gasket Stress Under ASME PCC-1

    Correct “gasket stress” is central to ASME PCC-1.To form a seal,bolts must compress the gasket into the serrated grooves of the flange.
    If stress is too low,fluid will leak past the gasket.
    Conversely,if stress is too high,the gasket may be crushed or the flange may deform.

    Balancing these factors proves particularly challenging when using corrosion-resistant alloys.While these materials offer high strength,they are prone to galling during tightening.
    Therefore,specifications emphasize the use of high-quality lubricants.Proper lubrication ensures that the torque applied to the nut is effectively converted into bolt load rather than lost to friction.

    Key Assembly Steps Defined by ASME PCC-1

    • Site Inspection:
      Technicians must check the flange faces for scratches or piqûre.Even a minor defect can create a leak path for high-pressure gas.
    • Alignment:
      The code mandates that flanges must be parallel.Forcing misaligned pipes together creates “residual stress.” This stress often leads to rupture par fatigue in the future.
    • Bolting Sequence:
      You should never tighten bolts in a simple circular order. Instead,ASME PCC-1 recommends a “Star” or “Cross-pattern” sequence.This ensures that the gasket compresses evenly across the entire surface.

    Bolt Tightening Methods and Tools

    MéthodeAccuracyCommon Use Case
    Manual TorqueModéréSmall diameter pipe fittings
    Hydraulic TorqueHautLarge flanges and high-pressure service
    Bolt TensioningTrès élevéCritical joints in offshore or nuclear plants
    Ultrasonic MeasurementAbsoluteHighly sensitive vacuum or toxic gas systems

    Qualifications for Bolting Technicians in ASME PCC-1

    An important update to ASME PCC-1 (Appendix A) focuses on the “human element.”It establishes a training and qualification program for bolting specialists.The code recognizes that the best materials can fail if the installer lacks proper training.
    Certification involves both theoretical knowledge and practical testing.Technicians must demonstrate they can handle ASME PCC-1 protocols for different gasket types.For example,a spiral wound gasket requires a different “feel” and torque than a soft PTFE gasket.

    Common Torque Values and Lubricant Factors

    This standard introduces the “nut coefficient” (K).It accounts for the friction forces within the thread.
    Lubricant TypeTypical Nut Factor (K)Impact on Torque
    Dry / No Lube0.20 – 0.30High friction;inconsistent bolt load
    Machine Oil0.15 – 0.20Moderate performance
    Molybdenum Disulfide0.10 – 0.13Consistent;highly recommended by PCC-1
    Nickel-Based Anti-Seize0.11 – 0.15Best for high-temp pipes

    Preventing Long-Term Issues

    By implementing this guide,you actively combat common operational failures.For instance,even-load distribution prevents the localized stresses that lead to fissuration sous contrainte due au sulfure in sour service.Furthermore,a properly tensioned joint can withstand the vibrations that typically cause fatigue failure in thinner-walled pipes.

    Nous contacter

    Prendre contact
    Trouvez-nous
    logo de Kaysuns

    Nous vous invitons à nous contacter

    Fourniture de
    Matériaux de tuyauterie en acier inoxydable et en alliage

    • Besoin d'une offre ?
    • Vous souhaitez connaître la dimension / le catalogue ?
    • Parler des problèmes techniques ?

    N'hésitez pas à nous contacter, nous nous ferons un plaisir de répondre à toutes vos questions.

    Obtenir un devis gratuit

    small_c_popup.png

    Obtenir un devis gratuit

    Vous souhaitez en savoir plus ? Contactez nous

    Nous vous répondrons dans les 24 heures. Merci !